| Northeast Remsco Construction,
Inc. bring your infrastructure and water treatment projects
the power of three specialized construction companies
with a long track record of success.
Completed projects for the public
and private sector in:
Shallow Cover Microtunnel Under
The Belt Parkway Nyc

Portions of the Borough of Queens
in New York City have historically been plagued with
flooding during major storm events, since most of the
Borough is relatively flat and at low elevations. The
Borough borders the East River and Long Island Sound
to the north and Jamaica Bay and the Atlantic Ocean
to the south. For many years the Borough has experienced
major storm water relief projects consisting of large
reinforced concrete single and multiple barrel sewers.
On November 24, 1998 the City of New
York Department of Design & Construction, (NYC DDC),
received bids for project SE-552D, Storm Sewers Crossing
the Belt Parkway. The low bid received was from Northeast
Construction Inc., Lakewood, New Jersey for $2,689,000.
The unusual project consisted of twin drives of 48"
Ø RCP under the Belt Parkway, open cut 48"
Ø RCP pipe and two major concrete chambers designed
to interconnect with existing storm box sewers providing
much needed additional storm water relief to an area
of Queens adjacent to John F. Kennedy Airport.
The NYC DDC engineers had to provide
a conduit under the Belt Parkway of sufficient capacity
for storm relief while meeting existing storm chamber
inverts on both sides. They determined that the required
capacity could be met by installing two 48" Ø
round pipes. The Belt Parkway is a heavily traveled,
six lane highway traversing a southern corridor through
the Borough of Brooklyn and Queens. Therefore, New York
City traffic engineers would not permit closure or narrowing
of the Belt Parkway traffic lanes. Further, physical
constraints prohibited the construction of a temporary
bypass or detour road, effectively eliminating the open
cut construction method.

The engineers chose microtunneling
for its safety and accuracy. Unfortunately, only 4 1⁄2
feet of cover would be available while tunneling under
the parkway. In recognition of the absence of the desirable
3 pipe diameters of cover, they chose to require pretreatment
of the granular soils with chemical grout to prevent
heave and/or settlement of the parkway roadbed.
To meet the project requirements,
Northeast Construction Inc. subcontracted the chemical
grout task to Hayward Baker, Inc. Hayward Baker's and
Northeast Construction's engineers chose to circumferentially
pre-grout the soils immediately outside the pipe limits.
Since the parkway could not be occupied during construction,
Hayward Baker utilized the Tube-a-Manchette method.
Thirteen (13) pipes were horizontally drilled from both
the jacking and receiving shafts, (see Fig. "A"),
and approximately 80,000 gallons of sodium silicate
grout were injected into the granular soils until permeability
tests yielded the desired results.
After several weeks of drilling and
grouting, Northeast Construction Inc. mobilized its
Herrenknecht AVN 1200T to the site together with Derrick
soil separation system. On September 15, 1999, after
working late hours in a race to beat the arrival of
hurricane Floyd, Northeast Construction completed the
second 183 lineal foot microtunnel drive and extracted
the MTBM from the receiving pit.
The jacked pipe and finished product
line was a Vianini 48" Ø RCP with 6"
wall, steel bell and concrete spigot. The AVN 1200T
was equipped with a soft ground head with 26 spade tools.
The AVN 1200T incorporates a new design with peripheral
drive motors, thereby permitting limited access to the
tunnel face through a center pressure bulkhead hatch.

The SE-552D contract concludes a series
of four (4) recent NYC DDC projects constructed to provide
additional storm sewer capacity to the southeast portion
of Queens.
Assistant Commissioner George Cowan,
P.E. headed the design group for the NYC DDC, while
Resident Engineer John Byrne, P.E., Supervising Engineer
Victor Ghazarian, P.E. and Borough Deputy Director William
Svilar, P.E. administered the construction activities
for the NYC DDC. Northeast Construction Inc. managed
the project with Superintendent George Gutierrez and
Project Manager
Richard Palmer, P.E.
As Prepared By:
Alberto G. Solana, P.E.
Vice President of Engineering
|