MEMORANDUM
October 4, 2004
TO: DARON JONES
FROM: BILL WALL
SUBJECT:
ARTICLE ON CABLE BURIAL NOV/DEC 2004 ISSUE
CALDWELL MARINE
INTERNATIONALCOMPLETES SUBMARINE CABLE INSTALLATION
FOR ORCAS POWER & LIGHT COOPERATIVE (OPALCO)
Caldwell Marine International
recently completed a turnkey submarine cable supply
contract for Orcas Power & Light Cooperative
(OPALCO). Opalco is the local electrical utility
for the San Juan Islands that are located off
the North West coast of Washington State.
The contract Scope of Work
called for the supply and installation of 2 lengths
of 69Kv composite submarine power cable with a
48 fiber unit embedded into the power cable and
the supply and installation of a Repeaterless
fiber optic submarine cable with 48 fibers. An
additional installation of an Opalco supplied
submarine fiber optic cable was also completed.
All the installations were between Islands in
the San Juan Archipelago.
Caldwell Marine International
mobilized a lay barge at the Port of Tacoma WA
and shipped all its specialized cable burial and
laying equipment from their base in New Jersey.
The power cable was manufactured under contract
to Caldwell by J-Power Systems out of Tokyo Japan
and shipped to Tacoma where a heavy lift operation
was used to transfer the 200 ton cable pan from
the freighter to the Caldwell barge. The submarine
Fiber Optic cable was manufactured under contract
to Caldwell by Ericsson out of their factory at
Hudiksvall, Sweden and shipped on a reel to the
barge at Tacoma.
The contract called for cable
burial of 1m to 1.25m burial depth in three of
the four inter-island links. Caldwell mobilized
their articulated Jet Plow with a 2 meter burial
stinger fitted for the main burial. Twin 440HP
surface deployed water pumps handled the Jet Plow’s
water supply. The Caldwell Jet Plow system is
equipped with the Caldwell Plow 2000 integrated
software package that is utilized for sending
commands to the plow from the surface control
station and receiving data topside from the plow.
INNOVATIVE
APPROACH TO EEL GRASS BED PRESERVATION
Opalco spent almost 2 years
preparing the data for the permits for this project.
When finally issued the permit “Window”
allowed installation only between August 16 and
October 30 2004, the contract was awarded in May
2004, so the clock was running. Of utmost importance
to both the environmental authorities and the
Opalco/Caldwell team was to ensure that the “Zostera
Marina” or Eel Grass areas were not impacted
by the cable burial operations. At two of the
landing sites there were eel grass beds that needed
to be traversed by the cable. To complete this
part of the project Caldwell designed and built
a low impact Jet-Assist Plow deployed directly
from a small barge. The Low Impact plow was deployed
during burial across the eel grass beds, and then
the main articulating plow was deployed once the
eel grass area was completed. The Low Impact burial
was very successful with little or no impact to
the Eel Grass beds, a marine biologist diver inspected
the site immediately after installation and shot
a video record of the installation.
As the industry knows all too
well many of today’s planned submarine utility
projects depend on getting a successfully issued
permit, this innovative approach to low impact
burial was pivotal in meeting the permit criteria
and avoiding a long and costly, post-lay mitigation
process. |